Status updates
- Now 12:07
- This weekend
-
May 2024 Next month
Find a postcode, place or road
A13
[A13] ALFREDS WAY (IG11) (Barking & Dagenham,Newham)
From: Monday 13 May 2024
To: Monday 20 May 2024
Last updated 11:46 Sunday 19 May 2024 : Traffic is slow moving through the works. Expect delays.
Works | Utility works
[A13] Alfreds Way (Eastbound) at the junction of Movers Lane - Eastbound lane one (of three) is closed due to emergency gas works.
A406
[A406] ANGEL ROAD (N18) (Enfield)
From: Friday 17 May 2024
To: Ongoing
Last updated 11:47 Sunday 19 May 2024 : Traffic is slow moving through the works.
Surface damage | Collapsed manhole
[A406] Angel Road (Eastbound) at the junction of Aberdeen Road - Lane one (of two) is closed due to a collapsed manhole cover
- [A406] ANGEL ROAD (N18) (Eastbound)
Blackwall Tunnel
[A102] BLACKWALL TUNNEL (E14,SE10) (Greenwich,Tower Hamlets)
From: Friday 17 May 2024
To: Monday 20 May 2024
Last updated 11:59 Sunday 19 May 2024 : Use other route. Traffic is queuing on all approaches to Rotherhithe Tunnel. Expect delays on diversion.
Works | TfL works
Silvertown Tunnel project - [A102] Blackwall Tunnel (Southbound) between A13 East India Dock Road and A102 Blackwall Tunnel Approach. - Tunnel closed southbound to facilitate weekend Silvertown Crossing works.
- [A102] BLACKWALL TUNNEL (E14,SE10) (Southbound)
- [A102] BLACKWALL TUNNEL NORTHERN APPROACH (E14) (Southbound)
- [A102] BLACKWALL TUNNEL (E14,SE10) (Southbound)
- [A102] BLACKWALL TUNNEL NORTHERN APPROACH (E14) (Southbound)
- [A102] BLACKWALL TUNNEL (E14,SE10) (Southbound)
- [A101] ROTHERHITHE TUNNEL (E14,E1W,SE16) (Southbound)
[A102] HOMERTON HIGH STREET (E9) (Hackney)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:13 Sunday 19 May 2024 : Traffic is slow in both directions on Kingsland High Street. Traffic is also slow eastbound on A12 East Cross Route. Expect delays.
Planned events | Sporting
Hackney Half Marathon 2024 -- There will be extensive local road closures in place from 0630. - [A102] Homerton High Street (All directions) at the junction of Digby Road - Hackney Half Marathon 2024 -- There will be extensive local road closures in place from 0630.
- [A102] HOMERTON HIGH STREET (E9) (Both directions)
- [A107] LOWER CLAPTON ROAD (E5,E8,E9) (Both directions)
- [A107] AMHURST ROAD (E5,E8) (Both directions)
- [A104] DALSTON LANE (E5,E8) (Both directions)
- [A107] MARE STREET (E8,E9) (All directions)
- [A1207] GRAHAM ROAD (E8) (Both directions)
- [A1207] GRAHAM ROAD (E8) (Both directions)
- [B108] QUEENSBRIDGE ROAD (E8) (Both directions)
- [A104] CRICKETFIELD ROAD (E5) (All directions)
- [A106] VICTORIA PARK ROAD (E9) (All directions)
[B4557] SOUTH WAY (HA9) (Brent)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:46 Sunday 19 May 2024 : Delays possible
Planned events | Sporting
Crawley Town vs Crewe Alexandra. - [B4557] South Way (All directions) wembley Stadium. - Skybet League Two Playoff Football Final - Wembley Stadium .Expect increased crowds and traffic congestion
A20
[A20] ELTHAM ROAD (SE12,SE3) (Greenwich,Lewisham)
From: Thursday 09 May 2024
To: Wednesday 22 May 2024
Last updated 11:47 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A20] Eltham Road (Westbound) between Hamlea Close and Leyland Road - Lane restrictions are in place as well as a closure of Leyland Road.
- LEYLAND ROAD (SE12) (Both directions)
A316
[A316] LOWER RICHMOND ROAD (TW9) (Richmond upon Thames)
From: Wednesday 09 August 2023
To: Friday 16 August 2024
Last updated 07:56 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A316] Lower Richmond Road (Both directions) at the junction of [A316] Lower Mortlake Road - Various restrictions in place to facilitate street works. Sandycombe Road is closed southbound.
- [A316] LOWER MORTLAKE ROAD (TW9) (Eastbound)
- [A316] LOWER RICHMOND ROAD (TW9) (Westbound)
- [B353] SANDYCOMBE ROAD (TW9) (Southbound)
- [B353] MANOR ROAD (TW9) (Northbound)
- [B353] MANOR ROAD (TW9) (Southbound)
A4
[A306] HAMMERSMITH BRIDGE (W6,SW13) (Hammersmith & Fulham,Richmond upon Thames)
From: Thursday 11 April 2019
To: Saturday 01 June 2024
Last updated 08:25 Saturday 18 May 2024 : Use an alternative route. Delays are possible.
Asset issues | Service disruption
[A306] Hammersmith Bridge (W6) (Both Directions) - The bridge is closed to all modes of transport apart from pedestrians and cyclists.
- [A306] HAMMERSMITH BRIDGE (W6,SW13) (Both Directions)
Blackwall Tunnel
[A102] BLACKWALL TUNNEL SOUTHERN APPROACH (SE10) (Greenwich)
From: Monday 25 March 2024
To: Wednesday 25 September 2024
Last updated 08:05 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A102] Blackwall Tunnel Southern Approach (Northbound) at the junction of [A2203] Blackwall Lane - The on-slip from Blackwall Lane is restricted due to Silvertown Tunnel works.
City Route
[A3211] VICTORIA EMBANKMENT SLIP ROAD (N) (EC4V,EC4Y) (City of London)
From: Wednesday 04 January 2017
To: Monday 30 September 2024
Last updated 10:14 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A3211] Victoria Embankment Slip Road N (Both directions) between [A201] Blackfriars Bridge and Horse Guards Avenue - Various carriageway restrictions are in place for the Tideway works. Northbound traffic on [A201] Blackfriars Road is diverted via [A3200] Stamford Street, [A301] Waterloo Bridge, [A4] Strand, Arundel Street and Temple Place. Southbound traffic on [A201] New Bridge Street is diverted via [A4] Fleet Street. The Cycle Superhighway has a new layout.. Find out more about the road changes at Victoria Embankment.
- [A201] VICTORIA EMBANKMENT (EC4V,EC4Y,SE1) (Both Directions)
- [A3211] VICTORIA EMBANKMENT (EC4Y,EC4V) (Both Directions)
- [A3211] BLACKFRIARS UNDERPASS (EC4Y,EC4V) (Eastbound)
Farringdon Cross Route
[A201] BLACKFRIARS BRIDGE (EC4V,SE1) (City of London)
From: Saturday 06 April 2024
To: Thursday 25 July 2024
Last updated 10:33 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
[A201] Blackfriars Bridge (Both directions) between [A201] Blackfriars Road and [A3211] Blackfriars Underpass - Cycle lane and lane 2 closures in place in both directions to facilitate works by City of London. New Bridge Street southbound lane 1 and Queen Victoria Street southbound lane 2 also closed.
Western Cross Route
[A3212] CHELSEA EMBANKMENT (SW11,SW1W,SW3) (Westminster,Kensington & Chelsea)
From: Friday 27 July 2018
To: Sunday 30 June 2024
Last updated 09:54 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A3212] Chelsea Embankment (SW11/SW3) (Both Directions) between Embankment Gardens and Chelsea Bridge - Various lane restrictions during Tideway Tunnel Project works. A new road layout remains in place for the duration of the works. More information on the Thames Tideway website.
- CHELSEA EMBANKMENT (SW3) (Both Directions)
PALMERSTON ROAD (E17) (Waltham Forest)
From: Saturday 18 May 2024
To: Saturday 08 June 2024
Last updated 11:10 Sunday 19 May 2024 : Use alternative route. There are no reported delays.
Works | Utility works
PALMERSTON ROAD WALTHAM FOREST, E17 - Palmerston Road (Both directions) between Mission Grove and Osborne Grove - Palmerston Road is closed in both directions at junction with Mission Grove to facilitate Thames Water works.
- PALMERSTON ROAD (E17) (Both directions)
[A219] WOOD LANE (W12) (Hammersmith & Fulham)
From: Monday 29 April 2024
To: Thursday 06 June 2024
Last updated 08:28 Saturday 18 May 2024 : Delays are possible.
Works | Utility works
[A219] Wood Lane (Both directions) at the junction of Macfarlane Road - Temporary signals in place to facilitate UK Power Networks works.
[A400] HAMPSTEAD ROAD (NW1) (Camden)
From: Saturday 06 October 2018
To: Sunday 31 May 2026
Last updated 08:27 Saturday 18 May 2024 : Delays possible.
Works | Service disruption
A400 Hampstead Road NW1 (Both Directions) between Granby Terrace and Robert Street - Lane restrictions and temporary signals at various junctions during junction improvement works in collaboration with HS2 works.
- [A400] HAMPSTEAD ROAD (NW1) (Both Directions)
- [A400] HAMPSTEAD ROAD (NW1) (Northbound)
THE MALL (SW1A) (Westminster)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:38 Sunday 19 May 2024 : Use an alternative route. No reported delays on diversion.
Planned events | Celebration
The Changing of the Guard - The Mall (All directions) at the junction of Queens Gardens - The Changing of the Guard will take place from 1100. Constitution Hill, the Queen Victoria Memorial, Spur Road, Link Road and The Mall (up to the junction with Marlborough Road) will be closed to vehicles between approximately 10.45am and 12.30pm on the days of Changing of the Guard. Expect crowds and increased traffic congestion.
- THE MALL (SW1A) (All directions)
- CONSTITUTION HILL (SW1A,SW1W) (Both directions)
- SPUR ROAD (SW1A,SW1E) (Both directions)
- BIRDCAGE WALK (SW1A,SW1E,SW1H) (Both directions)
- QUEENS GARDENS (SW1A) (Both directions)
- [A3214] BUCKINGHAM PALACE ROAD (SW1E,SW1W) (Both directions)
[A5] EDGWARE ROAD (NW2) (Barnet,Brent)
From: Friday 17 May 2024
To: Thursday 23 May 2024
Last updated 09:16 Sunday 19 May 2024 : No delays have been reported.
Works | Utility works
[A5] Edgware Road (All directions) at the junction of Gladstone Park Gardens - Three way temporary signals to facilitate UK Power Network works
Silvertown Tunnel, Greenwich Peninsula () ()
From: Friday 25 February 2022
To: Wednesday 31 December 2025
Last updated 07:56 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
Silvertown Tunnel project, Greenwich Peninsula - Various restrictions during Silvertown Tunnel-related works until 2025. https://tfl.gov.uk/travel-information/improvements-and-projects/silvertown-tunnel for More information.
- MILLENNIUM WAY (SE10) (Southbound)
- WEST PARKSIDE (SE10) (Northbound)
- EDMUND HALLEY WAY (SE10) (Eastbound)
- MILLENNIUM WAY (SE10) (Northbound)
- MILLENNIUM WAY (SE10) (Southbound)
- MILLENNIUM WAY (SE10) (Northbound)
- MILLENNIUM WAY (SE10) (Both directions)
[A112] HIGH STREET (E13) (Newham)
From: Monday 11 December 2023
To: Friday 31 May 2024
Last updated 10:02 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
[A112] High Street (Both directions) at the junction of [A114] Clegg Street - Temporary traffic signals in use to facilitate collaborative works.
[A4000] VICTORIA ROAD (NW10,W3) (Ealing)
From: Sunday 04 February 2024
To: Friday 28 June 2024
Last updated 08:26 Saturday 18 May 2024 : Delays are possible.
Works | Network Rail works
[A4000] Victoria Road (All directions) at the junction of [A4000] Wales Farm Road - Temporary traffic signals in use to facilitate rail works.
[A4127] GREENFORD ROAD (UB5,UB6) (Ealing)
From: Monday 02 October 2023
To: Saturday 15 June 2024
Last updated 08:27 Saturday 18 May 2024 : Delays are possible.
Works | Network Rail works
[A4127] Greenford Road (All directions) at the junction of Rockware Avenue - Temporary traffic signals are in place for HS2 works.
[A4205] PRAED STREET (W2) (Westminster)
From: Friday 03 May 2024
To: Thursday 13 June 2024
Last updated 10:17 Sunday 19 May 2024 : Delays are possible.
Works | Collaborative works
[A4205] Praed Street (All approaches) at the junction of London Street - Temporary traffic signals and various lane restrictions in place for development works.
LEADENHALL STREET (EC3A,EC3M,EC3V) (City of London)
From: Monday 08 April 2024
To: Sunday 19 May 2024
Last updated 10:44 Sunday 19 May 2024 : Use alternative route, delays are possible.
Works | Utility works
Leadenhall Street (Both directions) at the junction of Creechurch Lane - Road is closed due to gas connection works.
- LEADENHALL STREET (EC3A,EC3M,EC3V) (Both directions)
A205
A3
[A3] WEST HILL (SW15,SW18,SW19) (Wandsworth)
From: Wednesday 15 May 2024
To: Wednesday 22 May 2024
Last updated 12:02 Sunday 19 May 2024 : Traffic is slow moving in both directions on approach to these works.
Works | Utility works
[A3] West Hill (Both directions) between Keswick Road and Sutherland Grove - Temporary traffic signals in operation to facilitate utility works.
A12
[A12] COLCHESTER ROAD (RM3) (Havering)
From: Wednesday 27 July 2022
To: Sunday 31 August 2025
Last updated 10:02 Sunday 19 May 2024 : Delays are possible.
Works | Motorways works
[A12] Colchester Road (Both directions) between Petersfield Avenue and M25 J28 Brook Street Roundabout. - Single lane restrictions in operation to facilitate the creation of a new slip road and redesign of the Brook Street Roundabout. For more information see https://nationalhighways.co.uk/our-roads/south-east/m25-junction-28-improvements/
A20
[A20] LEE HIGH ROAD (SE13) (Lewisham)
From: Saturday 18 May 2024
To: Sunday 19 May 2024
Last updated 08:09 Sunday 19 May 2024 : No reported delays.
Works | Utility works
[A20] Lee High Road (Northbound) at the junction of Clarendon Rise - Bus lane closed northbound to facilitate Thames Water works.
A205
[A205] UPPER RICHMOND ROAD (SW15) (Richmond upon Thames,Wandsworth)
From: Tuesday 14 May 2024
To: Tuesday 21 May 2024
Last updated 08:09 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A205] Upper Richmond Road (All directions) at the junction of Dryburgh Road - Temporary traffic signals are in place to facilitate Thames Water works.
A205
[A205] STANSTEAD ROAD (SE23) (Lewisham)
From: Friday 17 May 2024
To: Wednesday 22 May 2024
Last updated 12:00 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A205] Stanstead Road (Both directions) at the junction of Colfe Road - A contra-flow is in operation to facilitate SGN works.
A23
[A23] PURLEY WAY (CR0) (Croydon)
From: Monday 29 April 2024
To: Wednesday 12 June 2024
Last updated 11:59 Sunday 19 May 2024 : Traffic is flowing well.
Works | TfL works
[A23] Purley Way (Both directions) at the junction of Waddon Road - Various restrictions including temporary signals during traffic signal improvement works. Thursday 18 April until Wednesday 1 May, inclusive, A23 Purley Way (Both directions) width restrictions. Thursday 2 until Wednesday 15 May, A23 (Northbound), lane one closed and A232 Croydon Road (Westbound), lane two closed. Thursday 16 until Wednesday 29 May, A23 (Both directions), lane three closed.
A3
[A3205] NINE ELMS LANE (SW11,SW8) (Lambeth,Wandsworth)
From: Friday 17 May 2024
To: Monday 20 May 2024
Last updated 12:03 Sunday 19 May 2024 : Minor delays on approaches.
Works | Utility works
[A3205] Nine Elms Lane (All approaches) at the junction of Ponton Road - Three-way temporary traffic signals in operation to facilitate BT works.
A3
[A243] LEATHERHEAD ROAD (KT9) (Kingston upon Thames)
From: Monday 22 April 2024
To: Friday 21 June 2024
Last updated 08:03 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A243] Leatherhead Road (Southbound) at the junction of Chalky Lane - Lane closure due to water works.
A40
[A40] WESTWAY (W10,W12) (Hammersmith & Fulham,Kensington & Chelsea)
From: Saturday 12 August 2023
To: Saturday 12 October 2024
Last updated 08:26 Saturday 18 May 2024 : Use alternative route. Delays are possible.
Works | TfL works
[A40] Westway (Eastbound) at the junction of [A3220] West Cross Route - Closure of off-slip to Northern Roundabout from the A40 to facilitate critical structural repairs. Traffic has to divert via the off slip at Wood Lane and back on the On slip from Wood Lane to access the roundabout. From 21/07-28/08 the A40 eastbound entry slip from Wood Lane and A3220 West Cross Route southbound are closed. From 02/09 until 12/10, the A3220 northbound West Cross Route and A40 westbound Wood Lane exit slip are closed. Lane restrictions will also be in in place at Wood Lane.
- [A40] WESTWAY (W10,W12) (Eastbound)
- [A40] WESTWAY (W10,W12) (Eastbound)
A41
[A41] BAKER STREET (NW1,W1U) (Westminster)
From: Saturday 18 May 2024
To: Sunday 19 May 2024
Last updated 11:15 Sunday 19 May 2024 : Use other route. Traffic is flowing well on diversion
Works | Utility works
[A41] Baker Street (Northbound) at the junction of Melcombe Street - Road closed northbound due to emergency man hole repairs.
- [A41] BAKER STREET (NW1) (Northbound)
A41
[A41] BAKER STREET (NW1,W1U) (Westminster)
From: Monday 16 January 2023
To: Thursday 23 May 2024
Last updated 10:07 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A41] Baker Street (Southbound) between Allsop Place and Melcombe Street, between Allsop Place and Melcombe Street - Various restrictions in place to facilitate London Underground upgrade works. Currently lane one (of two) closed southbound on Baker Street between Allsop Place Melcombe Street.
Bishopsgate Cross Route
[A10] GRACECHURCH STREET (EC3V,EC4N,EC4R) (City of London)
From: Monday 15 January 2024
To: Tuesday 30 July 2024
Last updated 09:25 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A10] Gracechurch Street (All approaches) at the junction of Leadenhall Street - Temporary signals are in place during works
Bishopsgate Cross Route
Southern River Route
[A3] BOROUGH HIGH STREET (SE1) (Southwark)
From: Saturday 18 May 2024
To: Sunday 19 May 2024
Last updated 11:12 Sunday 19 May 2024 : Approach with care. Traffic is flowing well.
Works | Utility works
[A3] Borough High Street (Both directions) at the junction of [B300] Union Street - Temporary signals in operation due to frame and cover repairs.
Inner Ring
[A5] EDGWARE ROAD (W1H,W2) (Westminster)
From: Monday 13 May 2024
To: Thursday 23 May 2024
Last updated 11:21 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A5] Edgware Road (Southbound) at the junction of [A5204] Seymour Street - Lane one (of two) southbound closed to facilitate Thames Water connection works.
Inner Ring
OLD STREET ROUNDABOUT (EC1Y) (Islington,Hackney)
From: Saturday 19 August 2023
To: Friday 31 May 2024
Last updated 10:04 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
Old Street Junction - Works for new road layout continue. Lane and footway restrictions are in place on Old Street and City Road. From Monday 22 April until Friday 31 May, various lane and directional closures will be in place between 22:00 and 05:00 each night.
- OLD STREET ROUNDABOUT (EC1Y) (All Directions)
- CITY ROAD (EC1V,EC1Y) (Northbound)
- OLD STREET (EC1V,EC1Y) (Westbound)
- PROVOST STREET (EC1V,N1) (All approaches)
[A124] WOOD LANE (RM10,RM7,RM8) (Barking & Dagenham)
From: Friday 17 May 2024
To: Sunday 19 May 2024
Last updated 11:11 Sunday 19 May 2024 : Use an alternative route. There are no reported delays.
Works | Utility works
[A124] Wood Lane (Westbound) at the junction of [A1112] Rainham Road North - Road closed due to emergency UKPN works.
- [A124] WOOD LANE (RM10,RM7,RM8) (Westbound)
[A24] EPSOM ROAD (KT17) (UNK)
From: Tuesday 14 May 2024
To: Tuesday 21 May 2024
Last updated 08:06 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A24] Epsom Road (Both directions) at the junction of Windmill Lane - Temporary traffic signals in place for SGN works.
[A4] TRAFALGAR SQUARE (SW1Y,WC2N) (Westminster)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:09 Sunday 19 May 2024 : Use an alternative route. There are no reported delays on diversion
Planned events | Exhibition
South African Elections - Voting - [A4] Trafalgar Square (All directions) at the junction of [A400] St Martins Place - South African Elections - Voting station. Additionally, Duncannon Street (Eastbound), closed between approximately 07:00 and 21:00 each day.
- [A4] DUNCANNON STREET (WC2N,WC2R) (Eastbound)
[A1010] HIGH ROAD (N17,N18) (Enfield,Haringey)
From: Sunday 19 May 2024
To: Ongoing
Last updated 09:21 Sunday 19 May 2024 : Use an alternative route. There are no reported delays.
Emergency service incidents | Police activity
[A1010] High Road (Both directions) at the junction of Moselle Place - The road is closed due to a police investigation.
- [A1010] HIGH ROAD (N17,N18) (Both directions)
[A3216] SLOANE STREET (SW1X) (Kensington & Chelsea)
From: Wednesday 28 December 2022
To: Tuesday 31 December 2024
Last updated 10:10 Sunday 19 May 2024 : Use an alternative route. Delays are possible on diversion
Works | Borough works
[A3216] Sloane Street (Northbound) between Sloane Square and Knightsbridge. - Road closure in place to facilitate Urban Realms Works.
- [A3216] SLOANE STREET (SW1X) (Northbound)
- [A3216] LOWER SLOANE STREET (SW1W) (Northbound)
- [A3216] SLOANE STREET (SW1X,SW3) (Northbound)
[A112] HOE STREET (E17) (Waltham Forest)
From: Wednesday 15 May 2024
To: Saturday 31 August 2024
Last updated 11:12 Sunday 19 May 2024 : There are no reported delays.
Works | TfL works
- Walthamstow Bus Station - [A112] Hoe Street (All directions) at the junction of Selborne Road - Walthamstow Bus Station will undergo essential maintenance works. Delays could become present in the immediate area caused by associated works vehicles and displaced buses.
[B283] HIGH STREET (KT3) (Kingston upon Thames)
From: Monday 13 May 2024
To: Monday 27 May 2024
Last updated 08:06 Sunday 19 May 2024 : Use an alternative route.
Works | Utility works
[B283] High Street (Both directions) between Blagdon Road and [A2043] Kingston Road - Road closed for Thames Water works.
- [B283] HIGH STREET (KT3) (Both directions)
[A4201] REGENT STREET (W1B,W1G,W1J,W1S,W1W) (Westminster)
From: Wednesday 08 May 2024
To: Thursday 23 May 2024
Last updated 10:56 Sunday 19 May 2024 : Use an alternative route. No reported delays on diversion.
Works | Utility works
[A4201] Regent Street (Northbound) between Hanover Street and New Burlington Street - Road closed for emergency Cadent Gas works.
- [A4201] REGENT STREET (W1B,W1G,W1J,W1S,W1W) (Northbound)
[B210] WELLINGTON STREET (SE18) (Greenwich)
From: Thursday 16 May 2024
To: Monday 20 May 2024
Last updated 08:07 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[B210] Wellington Street (Both directions) at the junction of Market Street - Temporary signals in place to facilitate electrical connection works.
[A105] GREEN LANES (N15,N22,N8) (Haringey)
From: Sunday 19 May 2024
To: Ongoing
Last updated 08:59 Sunday 19 May 2024 : Approach with caution.
Collisions | Vehicle collision
[A105] Green Lanes (All directions) at the junction of [A504] West Green Road - The road is restricted due to a collision. The traffic signals have been damaged.
[A3002] BOSTON MANOR ROAD (TW8) (Hounslow)
From: Wednesday 15 May 2024
To: Monday 03 June 2024
Last updated 08:28 Saturday 18 May 2024 : Delays are possible.
Works | Utility works
[A3002] Boston Manor Road (All directions) at the junction of Manor Vale - Temporary traffic signals are in place to facilitate Cadent Gas works.
[A232] CHEPSTOW ROAD (CR0) (Croydon)
From: Monday 13 May 2024
To: Wednesday 12 June 2024
Last updated 07:57 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A232] Chepstow Road (Both directions) at the junction of Park Hill Road - Various lane restrictions, road closures and temporary traffic signals are in place to facilitate TfL street lighting works at A232 Chepstow Rd, A232 Fairfield Rd, A232 Barclay Rd, Park Hill Rd, Park Lane Roundabout and Duppas Hill Road. Carriageway works will be undertaken weekdays between 21:30 and 05:00 over 12 phases with footway works between 08:00 and 16:30 each day. Phase 1 Carriageway works: 15 - 16 May, Chepstow Road is closed southbound between Radcliffe Road and Park Hill Rise.
[A2208] ROTHERHITHE NEW ROAD (SE16) (Southwark)
From: Monday 22 April 2024
To: Monday 03 June 2024
Last updated 08:09 Sunday 19 May 2024 : No reported delays.
Works | Utility works
[A2208] Rotherhithe New Road (All directions) at the junction of Galleywall Road - Temporary traffic signals are in place to facilitate UKPN works.
[A217] LONDON ROAD (CR4) (Merton)
From: Sunday 21 April 2024
To: Monday 27 May 2024
Last updated 08:04 Sunday 19 May 2024 : Use an alternative route.
Works | Utility works
[A217] London Road (Northbound) between Downe Road and Locks Lane - Road closure to facilitate ongoing gas main replacement works. In addition Bond Road is also closed.
- [A217] LONDON ROAD (CR4) (Northbound)
- BOND ROAD (CR4) (Northbound)
[A5] KILBURN HIGH ROAD (NW6,W9) (Brent,Camden,Westminster)
From: Monday 13 May 2024
To: Friday 30 August 2024
Last updated 08:14 Saturday 18 May 2024 : Delays are possible.
Works | Utility works
[A5] Kilburn High Road (All directions) between [B509] Belsize Road and Cambridge Avenue - Temporary signals in place to facilitate gas main works.
[A112] CONNAUGHT ROAD (E16) (Newham)
From: Tuesday 23 April 2024
To: Saturday 31 August 2024
Last updated 09:01 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
Airport Roundabout - [A112] Connaught Road (All directions) between Connaught Bridge and North Woolwich Roundabout - Various restrictions in place to facilitate borough works.
[A107] MARE STREET (E2,E8,E9) (Hackney,Tower Hamlets)
From: Sunday 19 May 2024
To: Ongoing
Last updated 10:59 Sunday 19 May 2024 : Traffic is flowing well in the area.
Planned events | Sporting
[A107] Mare Street (Both directions) at the junction of [A106] Victoria Park Road - Temporary signals in operation to facilitate the Hackney Half Marathon.
[A104] DALSTON LANE (E8) (Hackney)
From: Sunday 19 May 2024
To: Ongoing
Last updated 09:23 Sunday 19 May 2024 : There are numerous road closures in the area to facilitate this event. Expect increased numbers of pedestrians in the local area. All road users are requested to exercise caution.
Asset issues | Asset maintenance
[A104] Dalston Lane (Both directions) at the junction of [A1207] Graham Road - Temporary signals in operation due to Hackney Half Marathon.
[A1020] SILVERTOWN WAY (E16) (Newham)
From: Friday 29 December 2023
To: Thursday 06 June 2024
Last updated 09:01 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
[A1020] Silvertown Way (All approaches) at the junction of Caxton Street North - Temporary signals and lane restrictions in place.
A406
[A1] NORTH CIRCULAR ROAD (N2,N3,NW11,NW4) (Barnet)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:50 Sunday 19 May 2024 : Traffic is slow moving on approach. Expect delays.
Collisions | Vehicle collision
[A1] North Circular Road (Westbound) at the junction of [A598] Regents Park Road - Lane one (of four) is partially blocked by a collision.
A1
[A1] GREAT NORTH WAY (NW4) (Barnet)
From: Sunday 19 May 2024
To: Ongoing
Last updated 08:39 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A1] Great North Way (Both directions) at the junction of [A1] Fiveways Corner - Contra-flow in operation reducing the carriageway to a single lane in both directions during Thames Water works. Additionally, no access from the A41 (Northbound) to the A1 (Southbound).
A12
[A11] MILE END ROAD (E1) (Tower Hamlets)
From: Friday 17 May 2024
To: Sunday 26 May 2024
Last updated 10:23 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A11] Mile End Road (Westbound) between Beaumont Grove and [B121] Stepney Green - Cycle Superhighway 2 is closed to facilitate a temporary pedestrian walkway in the cycle lane during cable installation works.
A13
City Route
[A126] BUTCHER ROW (E1,E14,E1W) (Tower Hamlets)
From: Saturday 18 May 2024
To: Sunday 19 May 2024
Last updated 11:00 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A126] Butcher Row (Southbound) at the junction of [A13] Commercial Road - Lane one (of two) closed during Thames Water works.
A2
[A2] NEW CROSS ROAD (SE14) (Lewisham)
From: Monday 13 May 2024
To: Sunday 26 May 2024
Last updated 08:03 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A2] New Cross Road (Both directions) at the junction of Casella Road - Reduced to a single lane in both directions during Thames Water works.
A20
[A202] CAMBERWELL NEW ROAD (SE5) (Lambeth,Southwark)
From: Monday 13 May 2024
To: Friday 24 May 2024
Last updated 12:01 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A202] Camberwell New Road (Westbound) between [A215] Denmark Hill and Warner Road - Lane one restrictions in place to facilitate emergency gas works.
A205
[A205] ST MILDREDS ROAD (SE12,SE13,SE6) (Lewisham)
From: Sunday 19 May 2024
To: Monday 19 May 2025
Last updated 09:17 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
ST MILDREDS ROAD LEWISHAM, SE12 - [A205] St Mildreds Road (Eastbound) at the junction of Rayford Avenue - Lane width restriction to facilitate utility works.
A205
[A2216] LORDSHIP LANE (SE21,SE22,SE23) (Lewisham,Southwark)
From: Saturday 18 May 2024
To: Tuesday 28 May 2024
Last updated 08:07 Sunday 19 May 2024 : Delays are possible when restrictions are in place.
Works | Borough works
[A2216] Lordship Lane (Both directions) at the junction of [A205] Dulwich Common - Lane restrictions to facilitate Local Authority maintenance works.
A21
[A21] BROMLEY COMMON (BR2) (Bromley)
From: Friday 03 May 2024
To: Thursday 20 June 2024
Last updated 07:48 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A21] Bromley Common (Both directions) at the junction of [B265] Hayes Lane - Lane restrictions during emergency SGN works.
A4
[A4] BATH ROAD (TW6,UB3) (Hillingdon)
From: Monday 08 April 2024
To: Tuesday 18 June 2024
Last updated 08:25 Saturday 18 May 2024 : Delays are possible
Works | TfL works
[A4] Bath Road (All approaches) at the junction of Hatton Road North - Various restrictions in place to facilitate junction modernising work.
A4
[A4] KNIGHTSBRIDGE (SW1X,SW3,SW7,W1J,W2) (Kensington & Chelsea,Westminster)
From: Wednesday 03 April 2024
To: Wednesday 29 May 2024
Last updated 09:45 Sunday 19 May 2024 : Delays are possible.
Works | Collaborative works
The Berkeley Hotel refurbishment. - [A4] Knightsbridge (Westbound) between Old Barrack Yard and Wilton Place - Various restrictions during ongoing refurbishment works at The Berkeley Hotel. Reduced to one lane. Thursday 2 until Tuesday 14 May, Wilton Place (Both directions), closed. Tuesday 28 and Wednesday 29 May, A4 Piccadilly Underpass (Westbound), closed.
A40
A41
Inner Ring
[A5] EDGWARE ROAD (NW1,NW8,W1H,W2) (Westminster)
From: Monday 13 May 2024
To: Friday 26 July 2024
Last updated 11:33 Sunday 19 May 2024 : Traffic is flowing well.
Works | TfL works
[A5] Edgware Road (Both directions) between Praed Street and Newcastle Place. - Lane restrictions are in place to facilitate maintenance works.
A41
[A41] BAKER STREET (NW1,W1H,W1U) (Westminster)
From: Thursday 16 May 2024
To: Tuesday 21 May 2024
Last updated 11:31 Sunday 19 May 2024 : Traffic is flowing well.
Works | Collaborative works
[A41] Baker Street (All directions) between Crawford Street and [B524] Paddington Street - There are four way temporary signals at the location for utility works.
Farringdon Cross Route
Southern River Route
[A201] BLACKFRIARS ROAD (SE1) (City of London,Southwark)
From: Sunday 19 May 2024
To: Ongoing
Last updated 11:18 Sunday 19 May 2024 : Approach with care. Traffic is flowing well.
Works | Utility works
[A201] Blackfriars Road (Northbound) between Burrell Street and [A3200] Southwark Street - Lane one (of two) closed during Thames Water works. Additionally, the cycle lane is also closed.
Inner Ring
[A501] EUSTON ROAD (N1C,NW1,WC1H,WC1X) (Camden,Islington)
From: Thursday 16 May 2024
To: Sunday 19 May 2024
Last updated 11:20 Sunday 19 May 2024 : Approach with care. Traffic is flowing well.
Works | Utility works
[A501] Euston Road (Eastbound) at the junction of [A4200] Eversholt Street - Lane one closed to facilitate water works. Eversholt Street is also closed southbound between Grafton Place and Euston Road.
- [A4200] EVERSHOLT STREET (NW1) (Southbound)
Inner Ring
[A5200] GRAYS INN ROAD (WC1H,WC1N,WC1X) (Camden,Islington)
From: Saturday 11 May 2024
To: Wednesday 22 May 2024
Last updated 10:36 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
[A5200] Grays Inn Road (Northbound) at the junction of Britannia Street - Lane restrictions are in place during emergency Thames Water works.
Southern River Route
[A3203] LAMBETH BRIDGE (SE1,SW1P) (Lambeth,Westminster)
From: Wednesday 15 May 2024
To: Thursday 06 June 2024
Last updated 11:26 Sunday 19 May 2024 : Traffic is flowing well.
Works | TfL works
[A3203] Lambeth Bridge (Both directions) at the junction of [A3212] Millbank - Various lane restrictions during junction improvement works.
Western Cross Route
[A3220] HOLLAND ROAD (W11,W12,W14) (Kensington & Chelsea)
From: Monday 13 May 2024
To: Thursday 23 May 2024
Last updated 08:00 Saturday 18 May 2024 : Delays are possible.
Works | Utility works
[A3220] Holland Road (Both directions) at the junction of Lower Addison Gardens - Lane closures in place to facilitate utility work.
Western Cross Route
[A3220] HOLLAND ROAD (W11,W12,W14) (Kensington & Chelsea)
From: Thursday 16 May 2024
To: Thursday 23 May 2024
Last updated 11:35 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A3220] Holland Road (Northbound) at the junction of Russell Gardens - Lane one of two closed to facilitate urgent works.
[A219] FULHAM PALACE ROAD (SW6,W6) (Hammersmith & Fulham)
From: Friday 10 May 2024
To: Monday 20 May 2024
Last updated 09:04 Sunday 19 May 2024 : Traffic is flowing well.
Asset issues | Asset maintenance
[A219] Fulham Palace Road (Southbound) at the junction of Nella Road - The traffic signals have been damaged following a collision. Temporary traffic signals are in operation.
MOVERS LANE (IG11) (Barking & Dagenham)
From: Tuesday 02 April 2024
To: Sunday 08 September 2024
Last updated 11:34 Sunday 19 May 2024 : Use caution on approaches.
Works | Utility works
Movers Lane (Northbound) between [A13] Alfreds Way and [A123] Ripple Road - Temporary traffic signals to facilitate Cadent Gas works.
- MOVERS LANE (IG11) (Northbound)
[A504] WEST GREEN ROAD (N15) (Haringey)
From: Tuesday 07 May 2024
To: Friday 14 June 2024
Last updated 08:27 Saturday 18 May 2024 : Use alternative route. Delays are possible on diversion. .
Works | Utility works
[A504] West Green Road (Both directions) between High Road Tottenham and Westerfield Road - Road closed to facilitate gas main works.
- [A504] WEST GREEN ROAD (N15) (Both directions)
[A315] HIGH STREET (TW8,TW9) (Hounslow)
From: Wednesday 13 December 2023
To: Tuesday 23 July 2024
Last updated 08:24 Saturday 18 May 2024 : Delays are possible.
Works | TfL works
Cycleway 9: Extension to Hounslow. - [A315] High Street (Both directions) between A205 Chiswick High Road and A3002 Half Acre. - Various restrictions during works related to the extension of Cycleway 9 to Hounslow until late July. Temporary traffic signals and lane restrictions will be in place at various junctions as works progress. Additionally, footpaths will be closed with pedestrians re-directed to alternative safe routes. From Monday 18 March, three-way temporary signals will be in operation at the junction of Ealing Road for approximately two months.
- ALEXANDRA ROAD (TW8) (Both directions)
TUNNEL AVENUE (SE10) (Greenwich)
From: Monday 17 July 2023
To: Friday 17 January 2025
Last updated 08:06 Sunday 19 May 2024 : Delays are possible.
Works | TfL works
Tunnel Avenue (Southbound) at the junction of [A102] Blackwall Tunnel Southern Approach - Road closed for Silvertown Tunnel works
- TUNNEL AVENUE (SE10) (All approaches)
- TUNNEL AVENUE (SE10) (Southbound)
RED LION SQUARE (WC1B,WC1R,WC1V,WC1X) (Camden)
From: Monday 18 March 2024
To: Monday 01 July 2024
Last updated 09:51 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
Red Lion Square (Eastbound) at the junction of [A40] Procter Street - Red Lion Square is closed and there are lane restrictions in Proctor Street
- [A40] DRAKE STREET (WC1R,WC1X) (Westbound)
- [A401] THEOBALDS ROAD (WC1B,WC1N,WC1R,WC1X) (Westbound)
- RED LION SQUARE (WC1B,WC1R,WC1V,WC1X) (Both directions)
SURREY QUAYS ROAD (SE16) (Southwark)
From: Monday 13 May 2024
To: Friday 07 June 2024
Last updated 08:06 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
Surrey Quays Road (All directions) at the junction of Deal Porters Way - There are three way temporary traffic signals in operation during cable laying works,
[A4127] GREENFORD ROAD (UB6) (Ealing)
From: Friday 17 May 2024
To: Ongoing
Last updated 09:14 Sunday 19 May 2024 : Approach with caution. Traffic is flowing well.
Asset issues | Traffic signal fault
[A4127] Greenford Road (All approaches) at the junction of [A4127] Greenford Roundabout - The traffic signals are all out.
[A2] SHOOTERS HILL ROAD () ()
From: Sunday 19 May 2024
To: Ongoing
Last updated 10:10 Sunday 19 May 2024 : Traffic is flowing well.
Planned events | Ceremonial
Motorcycle Procession. - [A2] Shooters Hill Road (Both directions) at the junction of [A205] Academy Road - Expect Delays.
[A315] CHISWICK HIGH ROAD (W4) (Hounslow)
From: Friday 17 May 2024
To: Saturday 25 May 2024
Last updated 09:15 Sunday 19 May 2024 : The traffic is flowing well through the works.
Works | Utility works
[A315] Chiswick High Road (All directions) at the junction of Dukes Avenue - Temporary traffic lights in operation to facilitate urgent water works.
[A112] HOE STREET (E10,E17) (Waltham Forest)
From: Saturday 18 May 2024
To: Saturday 25 May 2024
Last updated 11:12 Sunday 19 May 2024 : There are no reported delays.
Works | Borough works
BAKERS AVENUE WALTHAM FOREST, E17 - [A112] Hoe Street (Northbound) at the junction of Bakers Avenue - Lane restrictions in operation to facilitate maintenance works.
[A503] SEVEN SISTERS ROAD (N4) (Hackney,Haringey)
From: Friday 17 May 2024
To: Sunday 19 May 2024
Last updated 09:08 Sunday 19 May 2024 : The traffic is flowing well through the works.
Works | Utility works
[A503] Seven Sisters Road (Eastbound) at the junction of Woodberry Grove - Lane one & two (of three) closed to facilitate Thames Water works.
[A235] LONDON ROAD (CR0,CR7) (Croydon)
From: Thursday 16 May 2024
To: Tuesday 21 May 2024
Last updated 08:07 Sunday 19 May 2024 : No reported delays.
Works | Utility works
[A235] London Road (Both directions) between Mayday Road and Stanley Road - Temporary traffic signals are in place while UK Power Networks carry out utility works.
[A215] CAMBERWELL ROAD (SE17,SE5) (Southwark)
From: Monday 13 May 2024
To: Friday 24 May 2024
Last updated 08:02 Sunday 19 May 2024 : Delays are possible.
Works | Utility works
[A215] Camberwell Road (Northbound) at the junction of [B214] Albany Road - Lane restrictions in operation to facilitate BT works.
THE MALL (SW1A,SW1Y) (Westminster)
From: Monday 02 October 2023
To: Thursday 30 May 2024
Last updated 09:58 Sunday 19 May 2024 : Use an alterative route. Delays are possible on diversion
Works | Construction activity
The Mall (Westbound) at the junction of Spring Gardens - The road is closed during construction by Admiralty Arch
- THE MALL (SW1A,SW1Y) (Eastbound)
[A124] BARKING ROAD (E6) (Newham)
From: Friday 26 April 2024
To: Monday 28 October 2024
Last updated 11:09 Sunday 19 May 2024 : Traffic is flowing well.
Works | Utility works
[A124] Barking Road (All approaches) at the junction of [A117] High Street South - Restrictions are in operation to facilitate utility works.
[A4] TRAFALGAR SQUARE (SW1Y,WC2N) (Westminster)
From: Sunday 19 May 2024
To: Ongoing
Last updated 12:02 Sunday 19 May 2024 : Traffic is flowing well. Expect an increase of pedestrians in the area.
Planned events | Demonstration/March
A group will form up and hold a static protest at location - [A4] Trafalgar Square (All directions) at the junction of [A4] Cockspur Street - A group will form up and hold a static protest at location
CONCERT HALL APPROACH (SE1) (Lambeth)
From: Monday 13 May 2024
To: Monday 24 June 2024
Last updated 09:41 Sunday 19 May 2024 : Delays are possible.
Works | Borough works
CONCERT HALL APPROACH LAMBETH, SE1 - Concert Hall Approach (All approaches) at the junction of [A3200] York Road - London Borough of Lambeth will be carrying out urban realm improvement works. Concert Hall Approach will be closed to facilitate the works.
[A404] HARROW ROAD (NW10) (Brent,Hammersmith & Fulham)
From: Saturday 15 June 2024
To: Ongoing
Last updated 09:17 Sunday 19 May 2024 : Traffic is flowing well through the works.
Works | Utility works
FURNESS ROAD BRENT, NW10 - [A404] Harrow Road (Both directions) at the junction of Furness Road - Temporary traffic signals in operation to facilitate water connection works.
[A1199] ST PAULS ROAD (N1) (Islington)
From: Wednesday 08 May 2024
To: Thursday 23 May 2024
Last updated 08:28 Saturday 18 May 2024 : Delays are possible.
Works | Utility works
[A1199] St Pauls Road (Both directions) at the junction of Wallace Road - Temporary traffic signals in operation to facilitate utility works.
[A104] DALSTON LANE (E8) (Hackney)
From: Saturday 11 May 2024
To: Monday 20 May 2024
Last updated 09:01 Sunday 19 May 2024 : The traffic is flowing well through the works.
Works | Utility works
[A104] Dalston Lane (Eastbound) at the junction of Laurel Street - Temporary traffic signals in place during repairs to a burst water main.